The commencement of the detailed zoning process for the Ertsmyra Næringsområde is announced. The announcement refers to plans to establish a data centre within the planning area.
Land is zoned for industrial use by Sirdal municipality.
Tonstad DataPark applies for a facility license.
NVE (Norges vassdrags- og energidirektorat) sends formal notice to potentially affected landowners regarding the facility license for Tonstad DataPark.
NVE consultation closes.
NVEs grants a facility license to Tonstad DataPark.
The municipality announces change in zoning with mention of data centre in the zoning plan.
Application to amend the zoning to add "data centre” (due to a national legislative change).
GreenScale announces intent to acquire Tonstad DataPark.
GreenScale completes acquisition of Tonstad DataPark.
GreenScale hosts first town hall meetings with residents and local/regional businesses.
Statnett allocates a 300MVA grid reservation.
GreenScale hosts town hall meeting with Josdal residents and cabin owners.
Site clearing work commences.
Anticipated frame permit submission.
Anticipated start of site levelling.
First building expected to be operational.
Whole campus operational.
For å gi deg de beste opplevelsene bruker vi teknologier som informasjonskapsler for å lagre og/eller få tilgang til enhetsinformasjon. Samtykke til disse teknologiene lar oss behandle data som nettleseratferd eller unike ID-er på dette nettstedet. Manglende samtykke eller tilbaketrekking av samtykke kan ha negativ innvirkning på visse funksjoner.